  • Primary Data Centre has started functioning at Navi Mumbai since 3rd April, 2013. Disaster Recovery Centre has been powered on at Mysore on 15-05-15. 
  • 28014 Departmental Post offices including mail offices and administrative offices have been networked at single Wide Area Network (WAN) and connected to Data Centre. 
  • Core Banking Solution (CBS) has been rolled out in 20494 Post Offices. ATMs have been installed in 759 locations. 
  • Core Insurance solution (CIS-PLI) has been rolled out in 25406 Post Offices. 
  • CSI Wave-1: Implementation of IDAM (Identity and Access Managerment) and SSO (Single Sign on) are under progress in Mysore Division. Other Wave-1 security components are at Data Centre level and they are under implementation. 
  • Anti-virus installed in 74,500 desktops 
  • Enterprise Monitoring System under CSI Wave-1 is a Data Centre level component and it is under implementation. 
  • CSI wave 2 Roll out: CSI has been rolled out In Mysore Division from 01.10.2015. Two HOs and Sixty three SOs were migrated to CSI in addition to NSH Mysore.
  • The following Legacy applications were integrated with CSI. 
  • eMOeMOePayment
  • Register net/ Parcel net
  • Speed net
  • IPS
  • IFS
  • RMFS
  • NPS 
  • UAT for Wave 2 & 3 solutions is in progress (Cycle 1 & 2 completed). 
  • CSI Integration UAT III completed from 22-06-2015 to 27-06-2015 at Hyderabad. 
  • Closure of defects of UAT III completed from 09th to 11th July 2015 at Hyderabad. 
  • Dispatch of RH Handheld devices started. 3546 devices have been dispatched to Branch Post Offices of Pilot circles.