Circle Union Wrote to CPMG, PMG and CHQ regarding Inaction in change of batteries in the UPSs in the POs of Phulbani division and insufficient bandwidth in NSP-II, making paralysation in day today work.

AIPEU-Gr. C Phulbani-762 001 <aipeuphi@gmail.com>

Fw: Inaction in change of batteries in the UPSs in the POs of Phulbani division and insufficient bandwidth in NSP-II, making paralysation in day today work-reg.
1 message

rc mishra <p3orissa@rediffmail.com>Wed, Jul 20, 2016 at 4:23 PM
To: cpmg_ori <cpmg_ori@indiapost.gov.in>, pmg_berhampur <pmg_berhampur@indiapost.gov.in>
Cc: nfpehq <nfpehq@gmail.com>, AIPEU GROUPC <aipeugrc@gmail.com>, ramniwasparashar61 <ramniwas.parashar61@gmail.com>, AIPEU-Gr C <aipeuphi@gmail.com>

N F P E
ALL INDIA POSTAL EMPLOYEES UNION GROUP-C
ODISHA CIRCLE BRANCH,BHUBANESWAR-751007
Trilochan Parida                                                                                              R.C.Mishra
 President                                                                                                        Circle Secretary
                                                                                   Vice-President CHQ & Leader RJCM
                                                                                            E-mail Ip3orissa@rediffmail.com
No. UN/AIPEU, Gr-C/Odisha/07-2016                                                Dated-20-07-2016.
To,                                                                                                                                                                             
         Sri Tilak De, IPoS.                                                              
         Chief Post Master General,
         Odisha Circle, Bhubaneswar-751001.
                   
          M/S Kalpana Rajsinghot, IPoS                                                                                                                         
          Post Master General,                                                                                                            
          Berhampur Region, Berhampur-760001.
Sub- Inaction for change of batteries of UPSs & for removal of insufficient bandwidth in NSP-II of the offices of Phulbani division- causing serious dislocation of work in CBS offices-reg.
Ref- Series of letters from this circle union.
Respected Sir/Madam,
      We are again attaching herewith this circle union’ letter through E-mail dated 22-06-2016 and also the letter of divisional secretary AIPEU, Gr-C, Phulbani division for favour kind action early to remove the dislocation of day to day works of the offices. It is to mention here that the transactions in the offices have been hampered severely in the offices due to frequent power failure and also due to low bandwidth in NSP-II, showing only normalcy of work by completion of the EOD of offices centrally.
    Though administration is claiming for full functioning of CBS finacle, the real picture in the offices in Phulbani division is totally different and there is total disruption of normal works. It is a matter of regrette that though this union has brought to the kind notice time & again, no remedial measure is forth-coming.
   It is once again requested for some tangible action for removal above problems as soon as possible for smooth running of offices in Phulbani division.
EXPECTING KIND RESPONSE & A LINE OF REPLY
WITH DUE REGARDS.
Yours faithfully

  (R.C.Mishra)      
Circle Secretary

Copy to- 1- Com. Rabinarayan Chaudhury, Divisional Secretary Phulbani division for information and necessary action..
               2- Com. R.N.Parashar, SG NFPE & G.S. AIPEU, Gr-C, CHQ,, New Delhi for favour of kind information. It is requested to kindly take up the case at CBS Directorate to resolve the problems.

 Circle Secretary


 From: "rc mishra"<p3orissa@rediffmail.com>
Sent: Wed, 22 Jun 2016 14:20:53
To: "cpmg_ori"<cpmg_ori@indiapost.gov.in>,"pmg_berhampur"<pmg_berhampur@indiapost.gov.in>
Subject: Inaction in change of batteries in the UPSs in the POs of Phulbani division and insufficient bandwidth in NSP-II, making paralysation in day today work-reg.


N F P E

ALL INDIA POSTAL EMPLOYEES UNION GROUP-C
ODISHA CIRCLE ,BHUBANESWAR-751007

TrilochanParidaR.C.Mishra
 President                                                                                                        Circle Secretary
                                                                                   Vice-President CHQ & Leader RJCM
                                                                                        E-mail ID-p3orissa@rediffmail.com
Letter No-UN/AIPEU,Gr-C/Odisha/06-2016                                        Dated-22-06-2016.
To, 
          Sri Tilak De, IPoS
          Chief Post Master General,
          Odisha Circle, Bhubaneswar-751001.

          MS Kalpana Rajsinghot, IPoS.
          Post Master General,
          Berhampur Region, Berhampur-760001.
Sub- Inaction in change of batteries in the UPSs in the POs of Phulbani division and insufficient bandwidth in NSP-II, making paralysation in day today work-reg.

Respected Sir/Madam,
        The matter of change of batteries of the UPSs was taken up with our PMG, Berhampur and we were assured for processing of the case and for action to change the batteries in the UPSs of the offices. But after a prolonged period of time no action has been noticed to be taken and the staff are taxed to innumerable hardship during frequent power failure without having proper back up. Similarly, the NSP-II of most of offices is having insufficient bandwidth for opening of finacle, causing untold hardship to staff, as well as public. So, there is great resentment of staff from all corners of the division towards inaction of the administration for any remedial action to all the above acute problems, putting staff to embracing conditions.

      We are attaching herewith the letter of divisional secretary, ventilating the resolutions taken in their General Body Meeting and it is urged for tangible action to remove the problems faced by staff & also to avert strong resentment in the division.

WITH REGARDS
Encl. As above.

Yours faithfully


(R.C.Mishra)
Circle Secretary
Copy to-1- Com. Rabinarayan Chaudhury, divisional secretary AIPEU, Gr-C, Phulbani division for information and necessary action.
               2- Com. R.N.Parashar, SG, NFPE & G.S. AIPEU, Group-C, CHQ, New Delhi for favour of kind information and he is requested to take up the case at Directorate level for early solution of the problems faced by staff in Phulbani division.


 Circle Secretary


From: "AIPEU-Gr. C Phulbani-762 001" <aipeuphi@gmail.com>
Sent: Mon, 20 Jun 2016 00:36:48
To: Phulbani DO-DoP <dophulbani.od@indiapost.gov.in>
Cc: AIPEU GROUPC <aipeugrc@gmail.com>, "AIPEU, Gr C, Odisha Circle" <p3orissa@rediffmail.com>
Subject: Union Resolutions regarding UPS problem and Link problem of Phulbani Division.
 
Inline image 1
To
            The Superintendent of Post Offices
            Phulbani Division
            Phulbani-762001

No- PHI/AIPEU Gr-C dated at Phulbani the 19th June 2016.


Ref-DO, Phulbani letter number B/G-43(C) dated 03.06.2016.

Sub-Resolutions adopted in the General Body Meeting of AIPEU Gr C Phulbani held on 19.06.2016 in the campus of Phulbani HO.

Sir
On 19th June 2016 a General Body Meeting of the AIPEU Gr-C, Phulbani divisional branch held at Phulbani HO, in the said meeting the following resolutions have been unanimously adopted.

  1. UPS Issues-
The UPSs of POs of Phulbani Division have no UPS backups for last two years due to non supply of UPS batteries. Which cause a lot of problems to the departmental staff as well as the general public, as frequent power cut is a frequent phenomena in Phulbani Division. Also this issue was taken into discussion with the SPOs Phulbani and the proposals have been submitted by DO, Phulbani to RO, Berhampur for replacement of batteries. Also the multiple queries made by the RO Berhampur had been complied the DO Phulbani at the earliest. Also the RO Berhampur had replied to our circle union vide letter no-EST/Union-1/2014 dated the 29th February 2016 that the proposals for replacement of batteries of POs of Phulbani Division have been received from Phulbani DO and the proposals will be processed on receipt of funds. But a matter of great resentment and regret is that though a remarkable time period has passed and also the 1/6th grant for 2016-2017 have been received no tangible action has been taken yet.

2.      Connectivity Issues-
In some areas of Phulbani Division 3G service is being provided by Airtel. Though the NSP-2 has been provided with Airtel dongle the same is not configured to access 3G network. If the same will be allowed to access 3G network the NSP-2 will provide that speed in which CBS work can be done i.e. half of the speed of NSP-1. But now the NSP-2 is providing the speed of 1/10th of NSP-1.  NSP-2 must provide the speed of half of the speed of NSP-1. This will give a lot relief to all offices and to public also. Also arrangement of NSP-2 to 11 offices which are already been migrated to CBS must be done at the earliest. Also 4-Port SIC cards must be supplied to Double Handed SOs of Phulbani Division. As according to Sify 4-Port SIC cards will boost the link speed, which is now reduced by using unmanaged switches.



So all the members present in the General Body Meeting unanimously resolved that if the above two problems of Phulbani Division will not be solved by 07th July 2016 or confirm a definite date by which the problems will be solved at any cost should be intimated this union by writing. Else the divisional union will be bound to go on trade union agitational programmes including strike.

This is for favour of kind information and necessary action.

Yours faithfully


                                          Rabinarayan Choudhury
Secretary, AIPEU-Gr C
Phulbani divisional branch
Phulbani (O) - 762001
Copy to-
1.      The General Secretary, AIPEU Gr C, CHQ, New Delhi-110008 for favour of kind information. And taking up the case at appropriate level with most priority as these cases are already intimated by this union’s memorandum number PHI/AIPEU/Gr C/01/05-2016 dated at 27th May 2016

2.      The Circle Secretary, AIPEU-Gr C, Odisha, Bhubaneswar-751007 for favor of information and necessary action at appropriate level.

3.      The CPMG, Odisha, Bhubaneswar-751001 for favour of kind information.

4.      The PMG, Berhampur-760001 for favour of kind information.


Rabinarayan Choudhury
Secretary, AIPEU-Gr C
Phulbani divisional branch
Phulbani (O) – 762001
____________________________________________________________



'Save a Tree. Please don't print this email or any documents unless you really need to'

No comments:

Post a Comment